Deepwater jetty construction

Scope:

Piling, heavy lifting, concrete batching station

Equipment:

Modular Jack-Up Barge "JB-108"

Date:

01 sep, 2019 – 31 mei, 2023

Location Icon

Location:

India

In the period 2019 - 2023, our modular jack-up barge JB-108 supported ITD Cementation India on their deepwater jetty dry bulk terminal construction project in Udangudi, Southern India. JB-108 was a decisive tool for this project, in which she was mainly engaging in piling, concrete batching, and heavy lifting operations. We are proud to say that throughout the challenging Covid-19 global epidemic circumstances, we managed to continue our service. On the basis of this succesfull co-operation, we built a relationship of trust with ITD Cementation and local supply chain partners, which continues until this day.

KEY PROJECT FEATURES 

  • 8 kM lONG DEEPWATER JETTY IN OPEN SEA
  • CHALLENGING SWELL CONDITIONS
  • PILING, CONCRETE BATCHING, HEAVY LIFTING
  • JB-108 KEY ELEMENT OF pROJECT WORKS
  • YEARS LONG TRUSTED RELATIONSHIP BUILT WITH CLIENT 

 

Frequently asked questions

The JB-104 has a maximum payload capacity of 400 tons, depending on load distribution and operational conditions.

Current: up to 2.0 m/s; Wind: up to 13 m/s; Wave height: 2.0 m preload / 1.0 m touch-down.

The JB-104 is equipped with 47.4-meter legs, a jacking stroke of 1.5 meters, and a jacking speed of approximately 15 meters per hour.